cycle-time-analyzer

v2026.09.24

Flow metrics analyzer (lead time, cycle time, throughput, WIP, aging WIP) for sprint and team health, with cumulative flow diagrams.

GitHub
Install command
npx skhub add borghei/cycle-time-analyzer
Markdown
SKILL.md

Cycle Time Analyzer (Flow Metrics)

Overview

Compute and visualize the four core Kanban flow metrics -- lead time, cycle time, throughput, and work-in-progress -- from issue history data exported from Jira, Linear, GitHub Projects, or any tracker that records status transitions. The output is a dashboard suitable for sprint retrospectives, executive reporting, and bottleneck analysis, plus a Mermaid cumulative flow diagram that visualizes work accumulation over time.

Flow metrics are the most useful diagnostic for team and process health, far more so than velocity or story points. Daniel Vacanti's work (Actionable Agile Metrics for Predictability, 2015) shows that predictability and throughput are governed by Little's Law (Throughput = WIP / Cycle Time), and that the most reliable way to improve delivery is to lower WIP and stabilize cycle time -- not to estimate harder. This skill also reports aging WIP (in-flight work older than the team's 85th-percentile cycle time -- the items most at risk) and supports the shared --format schema (json, markdown, mermaid, confluence, notion, linear).

Core Capabilities

  • Four flow metrics — lead time, cycle time (as a distribution, never an average), throughput, and WIP, tied together by Little's Law.
  • Aging WIP — flags in-flight items older than the 85th-percentile cycle time as at-risk; the most actionable daily metric.
  • Cumulative flow diagram — Mermaid CFD for retrospectives and exec reports.
  • Per-type filtering & trends — bug/feature/spike breakdowns over rolling 6-8 week windows across all six output formats.

When to Use

  • Sprint retrospective -- A team wants data-driven discussion of why some sprints feel slow.
  • Bottleneck investigation -- Throughput has fallen and the team needs to identify the constraining step.
  • Quarterly delivery review -- Leadership wants a real picture of delivery performance beyond story-point velocity.
  • Predictability analysis -- Stakeholders want delivery forecasts grounded in actual cycle time distributions (use with Monte Carlo via scrum-master/).
  • WIP-limit calibration -- A Kanban team is setting WIP limits and needs a baseline of current behavior.

When NOT to Use

  • For story-point velocity tracking, use scrum-master/velocity_analyzer.py.
  • For sprint capacity calculation, use scrum-master/sprint_capacity_calculator.py.
  • For per-person performance evaluation -- flow metrics are team-level signals; using them to rank individuals destroys the team behavior they measure.

Clarify First

Before running the analysis, confirm these inputs. If any is unknown or vague, ASK — do not assume:

  • Issue history with status transitions — per-item timestamps for when work started and finished (every metric is derived from these; missing transitions invalidate the numbers)
  • Workflow states that count as "in progress" vs "done" — your board's actual status names (defines where cycle time starts/stops, which changes every result)
  • Analysis window — the rolling period (e.g. last 6-8 weeks) and any type filter (scopes throughput trend and which in-flight items are flagged as aging WIP)

Stop rule: ask only the 2-3 that most change the output. If the user says "just draft it," proceed and list your assumptions at the top of the artifact.

Quick Start

python scripts/flow_metrics.py --input issues.json --format markdown   # full dashboard
python scripts/flow_metrics.py --input issues.json --format mermaid     # cumulative flow diagram
python scripts/flow_metrics.py --demo --format markdown                 # sample output, no input

Review the 85th-percentile cycle time (not the average), flag aging WIP that exceeds it, and re-run weekly to track the trend. See references/metrics-and-tool-reference.md for the full workflow, CLI flags, and JSON schemas.

Tools

ToolPurposeCommand
flow_metrics.pyCompute lead time, cycle time, throughput, WIP, aging WIP, CFDpython scripts/flow_metrics.py --input issues.json --format markdown

References

  • references/metrics-and-tool-reference.md -- Precise definitions of the four metrics, Little's Law, aging WIP, the 7-step workflow, troubleshooting matrix, success criteria, and the full flow_metrics.py CLI flags + input/output JSON schemas. Read when running an analysis or wiring up the tool.
  • references/flow-metrics-guide.md -- Vacanti-style deep dive: lead vs cycle, distributions vs averages, Little's Law, aging WIP, common anti-patterns. Read for narrative depth and tracker-specific export instructions.
  • references/red-flags.md -- Bad-vs-good examples of flow-metric reporting. Read this to sanity-check a dashboard before sharing it.
  • Vacanti, Daniel S. Actionable Agile Metrics for Predictability. ActionableAgile Press, 2015.
  • Vacanti, Daniel S. When Will It Be Done? ActionableAgile Press, 2020.
  • Little, John D. C. "A Proof for the Queuing Formula: L = λW." Operations Research, 1961.
  • Anderson, David J. Kanban: Successful Evolutionary Change for Your Technology Business. Blue Hole Press, 2010.

Scope & Limitations

In Scope:

  • Lead time, cycle time, throughput, WIP, aging WIP calculation
  • Cumulative flow diagram generation (Mermaid)
  • Per-type filtering (bug, feature, spike)
  • All six output formats per SHARED_OUTPUT_SCHEMA.md

Out of Scope:

  • Monte Carlo delivery forecasting (use scrum-master/velocity_analyzer.py)
  • Story-point velocity (use scrum-master/)
  • Resource capacity planning (use senior-pm/resource_capacity_planner.py)
  • Code-level metrics (PR review time, deploy frequency -- use DevOps-focused tools)

Important Caveats:

  • Flow metrics depend on accurate status transitions. If your team batch-updates the board once a day, the cycle time data will be discretized by that batch interval.
  • A team that gamifies flow metrics will produce better-looking numbers without changing real delivery. Use these metrics as a diagnostic, not a target. (Goodhart's Law.)
  • Cycle time is a team property, not an individual property. Resist the urge to compute per-assignee cycle time -- it will incentivize hand-offs that hurt the team.
  • AI-assisted teams: faster coding often shifts the wait into review and test states. Watch time-in-review and aging WIP there, not just total cycle time, and pair flow metrics with DORA rework rate. See the "AI-Assisted Delivery" sections in delivery-manager/ and scrum-master/.

Integration Points

IntegrationDirectionWhat Flows
scrum-master/ComplementaryFlow metrics + velocity together provide the full delivery picture
scrum-master/retrospective_analyzer.pyFeeds intoFlow trends inform retro topics
dependency-map/ComplementaryLong cycle times often correlate with cross-team dependencies
sprint-retrospective/Feeds intoCFD and aging WIP are standard retro inputs
senior-pm/project_health_dashboard.pyFeeds intoThroughput trends feed portfolio health
status-update-generator/Feeds intoWeekly status includes throughput and aging WIP highlights
agile-coach/Used byCoaches use flow metrics to assess team maturity
Discovery
Tags

No tags published for this skill.

Version
Latest version metadata

Version

v2026.09.24

Published

Sep 24, 2026